Batch HistoryMER-24003
MER-24003

Industrial Primer Gray

IPR-400
Complete
Station
SCL01
Operator
Jamal Martinez
Shift
Shift D
Batch Size
600 units
Scheduled
07/24/2026 09:00
Started
07/24/2026 09:00
Completed
07/24/2026 14:06
Duration
5h 7m

Execution Log

RM Receipt09:14· Jamal Martinez
SCL01 · std 15m · actual 14.8m
RM Staging09:37· Chen Wang
SCL01 · std 20m · actual 22.3m
Weigh & Charge09:59· Keira Chen
SCL01 · std 25m · actual 22.7m
Blending10:59· Ingrid Tanaka
BT01 · std 60m · actual 59.3m
Grinding11:40· John Dubois
DM01 · std 45m · actual 41.5m
Letdown12:12· Amara Tanaka
BT01 · std 30m · actual 31.6m
QA Pre-fill12:30· Tariq Hassan
SPE01 · std 20m · actual 18.4m
Equilibration12:45· Elena Kim
BT01 · std 15m · actual 15m
Fill & Pack13:29· Yuki Sharma
FL01 · std 45m · actual 43.7m
QA After-fill13:45· Keira Nakamura
SPE01 · std 15m · actual 16.3m
Shipping14:06· Jamal Martinez
N/A · std 20m · actual 21m

QA Release Results

TestSpecResultStatus
Yield≥ 98%99.2%Pass
Cycle Time≤ 341m307mPass
QC ReviewPassPassPass