Cv
CIVOPSfrom CivOps Manufacturing Systems
Operator
🔎pair scanner
Batch HistoryMER-24007
MER-24007

Industrial Primer Gray

IPR-400
Complete
Station
SCL01
Operator
John Dubois
Shift
Shift D
Batch Size
600 units
Scheduled
07/28/2026 13:00
Started
07/28/2026 13:00
Completed
07/28/2026 18:03
Duration
5h 4m

Execution Log

RM Receipt13:15· John Dubois
SCL01 · std 15m · actual 15.3m
RM Staging13:35· Amara Tanaka
SCL01 · std 20m · actual 19.8m
Weigh & Charge14:02· Tariq Hassan
SCL01 · std 25m · actual 27.4m
Blending14:56· Elena Kim
BT01 · std 60m · actual 54.3m
Grinding15:47· Yuki Sharma
DM01 · std 45m · actual 50.6m
Letdown16:13· Keira Nakamura
BT01 · std 30m · actual 26.2m
QA Pre-fill16:35· Jamal Martinez
SPE01 · std 20m · actual 21.6m
Equilibration16:49· Chen Wang
BT01 · std 15m · actual 13.8m
Fill & Pack17:30· Keira Chen
FL01 · std 45m · actual 41m
QA After-fill17:44· Ingrid Tanaka
SPE01 · std 15m · actual 14.6m
Shipping18:03· John Dubois
N/A · std 20m · actual 18.9m

QA Release Results

TestSpecResultStatus
Yield≥ 98%99.2%Pass
Cycle Time≤ 341m304mPass
QC ReviewPassPassPass