MER-24007
Industrial Primer Gray
IPR-400
Station
SCL01
Operator
John Dubois
Shift
Shift D
Batch Size
600 units
Scheduled
07/28/2026 13:00
Started
07/28/2026 13:00
Completed
07/28/2026 18:03
Duration
5h 4m
Execution Log
✓
RM Receipt13:15· John Dubois
SCL01 · std 15m · actual 15.3m
✓
RM Staging13:35· Amara Tanaka
SCL01 · std 20m · actual 19.8m
✓
Weigh & Charge14:02· Tariq Hassan
SCL01 · std 25m · actual 27.4m
✓
Blending14:56· Elena Kim
BT01 · std 60m · actual 54.3m
✓
Grinding15:47· Yuki Sharma
DM01 · std 45m · actual 50.6m
✓
Letdown16:13· Keira Nakamura
BT01 · std 30m · actual 26.2m
✓
QA Pre-fill16:35· Jamal Martinez
SPE01 · std 20m · actual 21.6m
✓
Equilibration16:49· Chen Wang
BT01 · std 15m · actual 13.8m
✓
Fill & Pack17:30· Keira Chen
FL01 · std 45m · actual 41m
✓
QA After-fill17:44· Ingrid Tanaka
SPE01 · std 15m · actual 14.6m
✓
Shipping18:03· John Dubois
N/A · std 20m · actual 18.9m
QA Release Results
| Test | Spec | Result | Status |
|---|---|---|---|
| Yield | ≥ 98% | 99.2% | Pass |
| Cycle Time | ≤ 341m | 304m | Pass |
| QC Review | Pass | Pass | Pass |