Batch HistoryMER-24001
MER-24001

Exterior Semi-Gloss Tint Base

ESG-200
Complete
Station
SCL01
Operator
Yuki Sharma
Shift
Shift B
Batch Size
400 units
Scheduled
07/22/2026 07:00
Started
07/22/2026 07:00
Completed
07/22/2026 12:09
Duration
5h 10m

Execution Log

RM Receipt07:14· Yuki Sharma
SCL01 · std 15m · actual 14.7m
RM Staging07:34· Keira Nakamura
SCL01 · std 20m · actual 19.4m
Weigh & Charge08:00· Jamal Martinez
SCL01 · std 25m · actual 26.3m
Blending08:54· Chen Wang
BT01 · std 60m · actual 53.8m
Grinding09:44· Keira Chen
DM01 · std 45m · actual 50.2m
Letdown10:18· Ingrid Tanaka
BT01 · std 30m · actual 34.2m
QA Pre-fill10:41· John Dubois
SPE01 · std 20m · actual 22.4m
Equilibration10:54· Amara Tanaka
BT01 · std 15m · actual 13.6m
Fill & Pack11:33· Tariq Hassan
FL01 · std 45m · actual 39.1m
QA After-fill11:50· Elena Kim
SPE01 · std 15m · actual 17.2m
Shipping12:09· Yuki Sharma
N/A · std 20m · actual 18.7m

QA Release Results

TestSpecResultStatus
Yield≥ 98%99.2%Pass
Cycle Time≤ 341m310mPass
QC ReviewPassPassPass