MER-24006
Metallic Silver Topcoat
MTS-300
Station
SCL01
Operator
Ingrid Tanaka
Shift
Shift C
Batch Size
200 units
Scheduled
07/27/2026 12:00
Started
07/27/2026 12:00
Completed
in progress
Duration
304m (est)
Execution Log
✓
RM Receipt12:14· Ingrid Tanaka
SCL01 · std 15m · actual 14.8m
✓
RM Staging12:33· John Dubois
SCL01 · std 20m · actual 19.1m
✓
Weigh & Charge12:55· Amara Tanaka
SCL01 · std 25m · actual 21.3m
✓
Blending13:58· Tariq Hassan
BT01 · std 60m · actual 63m
✓
Grinding14:43· Elena Kim
DM01 · std 45m · actual 45.1m
✓
Letdown15:10· Yuki Sharma
BT01 · std 30m · actual 26.9m
✓
QA Pre-fill15:32· Keira Nakamura
SPE01 · std 20m · actual 22.5m
✓
Equilibration15:45· Jamal Martinez
BT01 · std 15m · actual 13.1m
✓
Fill & Pack16:26· Chen Wang
FL01 · std 45m · actual 40.9m
✓
QA After-fill16:41· Keira Chen
SPE01 · std 15m · actual 14.4m
…
Shippingrunning· Ingrid Tanaka
N/A · std 20m · actual 22.8m
QA Release Results
| Test | Spec | Result | Status |
|---|---|---|---|
| Yield | ≥ 98% | 99.2% | Pass |
| Cycle Time | ≤ 341m | 304m | Pass |
| QC Review | Pass | Pass | Pass |