Batch HistoryMER-24011
MER-24011

Industrial Primer Gray

IPR-400
Released
Station
SCL01
Operator
Yuki Sharma
Shift
Shift D
Batch Size
600 units
Scheduled
08/01/2026 17:00
Started
08/01/2026 17:00
Completed
08/01/2026 22:08
Duration
5h 9m

Execution Log

RM Receipt17:16· Yuki Sharma
SCL01 · std 15m · actual 16.6m
RM Staging17:36· Keira Nakamura
SCL01 · std 20m · actual 19.7m
Weigh & Charge17:58· Jamal Martinez
SCL01 · std 25m · actual 21.9m
Blending18:50· Chen Wang
BT01 · std 60m · actual 52.3m
Grinding19:37· Keira Chen
DM01 · std 45m · actual 46.5m
Letdown20:10· Ingrid Tanaka
BT01 · std 30m · actual 33.5m
QA Pre-fill20:29· John Dubois
SPE01 · std 20m · actual 18.8m
Equilibration20:43· Amara Tanaka
BT01 · std 15m · actual 13.9m
Fill & Pack21:34· Tariq Hassan
FL01 · std 45m · actual 51.6m
QA After-fill21:48· Elena Kim
SPE01 · std 15m · actual 13.9m
Shipping22:08· Yuki Sharma
N/A · std 20m · actual 20.2m

QA Release Results

TestSpecResultStatus
Yield≥ 98%99.2%Pass
Cycle Time≤ 341m309mPass
QC ReviewPassPassPass